No. | Component | Characteristic | Type
of | Quantum | Ref.td./Acceptance | Format of Records |
| A. MATERIAL | ||||||
| 1. | Plates,
| Surface
defects i.e. Pitting, Rolling Marks etc.and | Visual & Dimensiona | 100% | As
per requirement
| Material
Inspection |
| 2. | Material as above except for pipes verificatio of mill Test Report. | Mechanical
& Chemical Properties, | Mill
Test
| 100% | _____
Do _______ | Material Identification Report |
| 3. | Pipes Seamless or Welded C.S./S.S. | mechanical & Chemical Properties | Tensile
/ Flattering and chemical | 100% | A 106 IS 1239 | Lab.T.C. |
| 4. | Casting / Forgings | Surface Defects Dimensions
| Visual Dimensional
| 100% | As per requirements comparing with approved drugs & given Std. specification. | Material Inspection Reprot. |
| 5. | Casting / Forgins | Mechanical & Chemical Properties, Ultrasonic,NBT. | Physical
& Chemical | 100% | _______Do______ | Material Identification Report with Lab. T.C. |
| B. BOUGHT OUTS | ||||||
| 6. | Fastners | From reputedMafg. | Visual Dimensional | Sample | As
per requirement
| Material
Inspection |
| 7. | Gasket, 'o' Ring Packing Material | From Reputed Manufacturer | Visual Dimensional | 100% | As per app. Drgs. Client Requirements. | With Mrg. test Certificate |
| 8. | Glass Tubes & Sheets | From Reputed Manufacturer | ___Do____ | 100% | As per App. Drg/given Std. Specification | Material Inspection Report |
| 9. | Magnets | From Reputed Manufacturer | ___Do____ | 100% | ___Do____ | ___Do____ |
| C. IN PROCESS | ||||||
| 1. | Procedure & Welder | Suitability of Procedure & Welder | Mechani-Majorcal Testing of Weld Test Coupon. | 100% | ASME Sec VIII & Sec IX | PDR & Welder Qualificatiion Record. |
| 2. | Marking | Templates, Flanges Profile Pipes, etc. | Measurement | 100% | As per Approved Drg. of Manufacturer | Internal Meno & Insp. Checking Report. |
| 3. | Identification | Marked Material | Checking
Staping | 100% | ___Do____ | ___Do____ |
| 4. | Cutting | ___Do____ | Sizes
| 100% | ___Do____ | ___Do____ |
| 5. | Maching & Stap Transfer | Dimensional Checkup Intermediate & Final & Stap Transfer | Dimensioal | 100% | ___Do____ | ___Do____ |
| 6. | Set-up & Fitment of Nozzeles ect. | Dimensional & Confirmity orientation | Visual
& Dimensional | Major 100% | As per apprd. Drg and std. Specification | ___Do____ |
| 7. | Welding | Root urn welding & Welding | Visual
D.P. Test | Major | ___Do____ | ___Do____ |
| 8. | Assembly | ___Do____ | ___Do____
| Major 100% | ___Do____ | ___Do____ |
| 9. | Testing | Leak Tightness | pneuatic
Hydraulic | Critical 100% | No leak Drg. | ___Do____ |
| 10. | Painting & Cleaning | Surface finished Special | Visual | 100% | As per Apprd, Drg. of Mfg. | ___Do____ |
| 11. | Final Inspection after Painting | A)Final
Finish and Appearance | Visual | 100% | Good Finish | Final Release Note |